Power Agency Lights up Gonder with 246m Br




Ethiopian Electric Power has upgraded and expanded a distribution station located in Gonder for 246 million Br.

The project took one year to complete, and it has begun operation with full capacity last month, according to Dawit G.Egziabher, the project site manager.

The expansion project upgraded the station’s distribution capacity from 40MW to 166MW and installed two new transformers that can carry 15,000 volts of electricity.

These upgrades have relieved the power interruptions that were cause for a lot of complaints from the four industrial parks in Azezo, according to Dawit.

In addition to Gonder, the upgrade will also benefit its neighbouring towns



Published on Dec 08,2018 [ Vol 19 ,No 971]


SHARE :
               


Editorial

With a reformist administration in charge of the executive, there has b...


Agenda

The new electricity tariffs that became effective on December 1, 2018,...


Fineline

Who it is that midwifed the rapprochement between E...


Commentary

Ethiopia’s economy is at a crossroads. The same old advice will not s...


Viewpoint

A recent photo between Prime Minister Abiy Ahmed (PhD) and George Soros...


Opinion

The future is bleak. Millennials and younger generations who will inher...


View From Arada

There is heated debate on the propriety, decency and morality of breast...




Business Indicators




ADVERTISEMENT



Editors Pick















//